2024
Expansion of the onshore and offshore sections of the LNG Terminal in Świnoujście.
Client: | PORR S.A. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Świnoujście |
Project type: | Comprehensive laboratory services in the field of geotechnical testing, concrete mix testing, and concrete testing. |
Execution time: | 2020-2024 |
Construction of the Koszalin and Sianów bypass on the S6 expressway, including the S11 section from the Bielice interchange to the Koszalin West interchange, from km 6+400 to km 14+300.
Client: | Polbud-Pomorze Sp. z o.o. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Koszalin |
Project type: | Comprehensive laboratory services in the field of geotechnical testing, concrete mix and concrete testing, as well as mineral-asphalt mixtures and bituminous pavement testing. |
Execution time: | 2021-2024 |
Construction of two gas-steam units at PGE Górnictwo i Energetyka Konwencjonalna S.A., Dolna Odra Power Plant Branch.
Client: | Polimex Budownictwo Sp. z o.o. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Dolna Odra |
Project type: | Comprehensive laboratory services in the field of geotechnical testing, concrete mix, and concrete testing. |
Execution time: | 2021-2024 |
Construction of National Road DK11 on the section from the Janiska roundabout to the Kołobrzeg East interchange.
Client: | PORR S.A. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Kołobrzeg |
Project type: | Comprehensive laboratory support in the field of geotechnical testing, concrete mix, and concrete testing. |
Execution time: | 2022-2024 |
2023
Construction of the S11 road Koszalin–Szczecinek, section from the Koszalin West interchange (excluding the interchange) to the Bobolice interchange.
Client: | Mostostal Warszawa S.A. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Koszalin - Szczecinek |
Project type: | Comprehensive laboratory services in geotechnical testing, concrete mix and concrete testing, as well as bituminous pavement testing. |
Execution time: | 2020-2023 |
2022
2021
2020
Panattoni Park Szczecin – Załom – Halls C1-C2 with social and office facilities
Client: | Eko Montex |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Szczecin |
Project type: | Comprehensive laboratory services in the field of geotechnical testing, concrete mix testing, and concrete testing. |
Execution time: | 2019-2020 |
2019
Extension of the Florian Krygier Stadium in Szczecin
Client: | Extension of the Florian Krygier Stadium in Szczecin |
Testing department: | BETOTEST POLSKA Sp. z o. o |
Location: | Szczecin |
Project type: | Comprehensive laboratory service related to geotechnical tests as well as concrete and concrete mixture testing |
Execution time: | July 2019 - now |
Delivery of 492 prestressed segments for a bridge in Denmark connecting Marbæk and Tørslev Hage.
Client: | Mostostal Warszawa S.A. |
Testing department: | BETOTEST POLSKA Sp. z o.o. |
Location: | Szczecin |
Project type: | Comprehensive laboratory support in the field of concrete mix and concrete testing. |
Execution time: | 2018-2019 |